Minutes, IBIS Quality Committee 08 September 2015 11:00-12:00 EST (08:00-09:00 PST) ROLL CALL eASIC: David Banas Ericsson: Anders Ekholm Intel: Michael Mirmak Eugene Lim IO Methodology * Lance Wang Signal Integrity Software * Mike LaBonte Teraspeed Labs: * Bob Ross Everyone in attendance marked by * NOTE: "AR" = Action Required. -----------------------MINUTES --------------------------- Mike LaBonte conducted the meeting. Call for IBIS related patent disclosures: - None Call for opens: - None ARs: - Mike add comments to CMPNT, DLY, MSPEC sections. - No new progress. - Lance add comments to EBD section. - No new progress. - Bob add comments to CIRCUIT section. - No new progress. Possible IBIS quality summit presentation - Mike: If we release the UG we could report on that. - People are always interested in parser release information. - Bob: We probably will not release the UG soon enough. - Mike: We could have just a few slides in the chair's report. - Bob: That would be good. Parser Contract review: - Bob: The agreement has been signed by all parties. - The code might be delivered some time in October. DLL Checking: - Mike showed DLL_checks_draft1.docx. - Mike: This is intended to be an appendix to the parser contract. - Bob: Is there a way to check the DLL before opening it? - Mike: Not really, but failure to open the DLL is not fatal. - Bob: We do not want repeated warnings. - Mike: It checks each AMI file only once, can do the same for DLLs. AR: Mike send DLL_checks_draft2.docx to Bob with more code details. Meeting ended: 11:51 ET Next meeting Sep 15, 2015